Ongoing work related to the modernisation of the sidewalk. Goods in Elk (a handle to the cemetery # 2). The contractor does not provide for major traffic problems. However, special attention should be given to the current marking area. The total cost of the work is about 89 000 zł.

As part of the investment will be made walkway. Goods in Elk (a handle to the cemetery # 2), ok. 2 m with the main entrances on the ok. 300 m.

The work will be included:

·         demolition of concrete curb and paving with concrete block

·         setting concrete kerbs

·         you set the concrete edging

·         the execution of paving sidewalk with concrete block

·         addition to the asphalt pavement with curb mass of mineral-asphalt

·         regulating Street outlets

The contractor is the company CI MATEX Matthew Wojsiat in Elk.
The total cost of the work is 88990.50 thousand. zł.

Scheduled completion of work is the beginning of December 2017.

The contractor does not provide for major traffic problems. However, special attention should be given to the current marking area.